1Verify pipe material and wall thickness match the WPS (Welding Procedure Specification)
2Complete fill and cap passes using SMAW or FCAW
3Bevel pipe ends to 37.5° and clean to bright metal
4Visually inspect and mark weld with welder ID
5Weld root pass using GTAW (TIG) process
6Set up argon back-purge inside the pipe
7Weld hot pass immediately after root to prevent cracking
8Fit up joint with proper root gap (1/8") using tack welds