Standby Generator Hookup

Electrical

Year 3-460 XP

Order the steps for connecting a standby generator with an automatic transfer switch.

Drag to reorder, or use the arrow buttons.

1Connect utility (normal) power to ATS line side
2Simulate power outage and verify automatic start, transfer, and retransfer
3Run conduit and conductors from generator to automatic transfer switch (ATS)
4Program ATS for transfer settings and exercise schedule
5Install the generator on a level concrete pad with required clearances
6Install the ATS adjacent to the main panel
7Connect ATS load side to emergency panel or selected circuits
8Connect generator output to ATS generator side