1Remove load incrementally, run at no-load for cool-down, then shutdown
2Increase to 100% rated load and run for minimum 2 hours per NFPA 110
3Verify fuel day tank level and fuel supply system operation
4Increase to 50% rated load and monitor temperatures and pressures
5Start generator at no-load and verify stable voltage and frequency
6Increase to 75% rated load and verify all parameters within limits
7Apply 25% load from load bank and monitor for 30 minutes
8Inspect generator — check oil level, coolant, belts, and battery charger